Free project plan template
Plan a project from start to finish with goals, scope, deliverables, timeline, team roles, budget and risks. Sample plan included.
What's in this template
PROJECT PLAN Clinic appointment app Hollybrook Medical Group · Project manager: Siobhan Kelly · Version 1.2 · 5 October 2026 |
16 weeks 2 November 2026 to 19 February 2027 | £145,000 Approved budget | 9 clinics Live at launch |
Background
Patients at our nine clinics book appointments by phone. Lines are busiest between 8:00 and 9:00, and 30% of callers give up before reaching reception. A booking app will free up reception staff and make it easier for patients to see a doctor.
Goals
- Let patients book, change and cancel appointments online, 24 hours a day
- Move 40% of bookings online within six months of launch
- Cut missed appointments by 25% with text and app reminders
Scope
In scope: iOS and Android app, web booking page, reminders by text and push notification, staff dashboard, link to the EMIS patient system.
Out of scope: video consultations, repeat prescriptions and payments (planned for phase 2).
Deliverables and timeline
Phase | Deliverable | Dates |
|---|---|---|
1. Discovery | Requirements and patient research | 2 to 20 November |
2. Design | Clickable prototype tested with 15 patients | 23 November to 18 December |
3. Build | App, web page and staff dashboard | 4 January to 5 February |
4. Test | Accessibility, security and pilot at Hollybrook Road clinic | 8 to 12 February |
5. Launch | All nine clinics live | 19 February 2027 |
Team and roles
Name | Role | Responsible for |
|---|---|---|
Siobhan Kelly | Project manager | Plan, budget, reporting |
Dr Imran Siddiqui | Clinical lead | Clinical safety sign-off |
Hannah Price | Product designer | Research, prototype, app design |
Callum Reid | Lead developer | Build, EMIS integration |
Joy Mensah | Practice manager | Staff training and rollout |
Budget
Item | Cost |
|---|---|
Design and research | £22,000 |
Development | £88,000 |
Testing and security review | £15,000 |
Training and launch | £8,000 |
Contingency (8%) | £12,000 |
Total | £145,000 |
Risks
Risk | Likelihood | Mitigation |
|---|---|---|
EMIS integration takes longer than planned | Medium | Start integration work in week 1 of build |
Older patients find the app hard to use | Medium | Test with patients over 70; keep phone booking open |
Staff resist the change | Low | Involve reception teams in design; train early |
Approval
Approved by the Hollybrook Medical Group board on 1 October 2026.