Free project status report template

Update stakeholders on a project with overall status, key numbers, milestones, risks, budget and decisions needed. Sample report included.

What's in this template

PROJECT STATUS REPORT

Customer portal rebuild

Week ending 9 October 2026 · Project manager: Deepa Raghavan · Sponsor: William Carter

Overall status At risk Payments integration is one week behind. Launch date still achievable.

68%

Work complete

$412k

Spent of $600k budget

7

Weeks to launch

3

Open risks

Summary

The new login, account and billing pages are finished and in testing. Integration with the payments provider is running one week late because their sandbox was down for four days. We have moved two developers onto it and expect to recover the time by 30 October.

Progress this week

Next week

Milestones

Milestone

Due

Status

Designs signed off

4 September

Done

Core pages built

2 October

Done

Payments integration

23 October

1 week late

User acceptance testing

13 November

Not started

Launch

27 November

On plan

Risks and issues

Risk

Impact

Owner

Action

Payments sandbox outages

High

Tomasz Nowak

Daily check-in with provider; mock service for testing

Load testing not yet booked

Medium

Grace Liu

Book test window for week of 9 November

Support team training time

Low

Deepa Raghavan

Record training videos in advance

Budget

Budget

Spent

Forecast

Labour

$480,000

$338,000

$492,000

Software and hosting

$80,000

$54,000

$78,000

Contingency

$40,000

$20,000

$30,000

Total

$600,000

$412,000

$600,000

Decisions needed

Find it in: Project plan template

More business templates · All templates